Thursday, April 16, 2009

PRIMING.....TOO MUCH WHITE.....

So Myles took yesterday off and spent the whole day priming everything. So it's all white now. Lots of white....
White walls.
White kitchen.
White trim.
Need some color..





Exterior trim....white

KITCHEN & BATH

The kitchen installed....
Well sortof, the installer just up left and half the hardware isn't on yet! These kitchen guys really amaze me, told me that I couldn't use my own hardware, the installer wouldn't install it, had to pick from their selection. So I did and he couldn't installed those anyway, didn't have the appropriate washers or something. So now it's a deficiency. Oh well, our finisher seems really great so we will probably have him finish half the kitchen as I have no faith that the kitchen guys will do it (maybe they will surprise me). I will be holding back 5% (didn't notice it wasn't 10% which is standard) so if they want that they need to complete everything, and I mean everything or they are not getting any of it.
But it looks nice, which is the most important...



Some parts are still purple so ignore color...





Heating pad for the upstairs washroom. I glad we added this, it will be a really nice feature (I hate it when my feet are cold!) Took the electrician about 1/2 hour to installed.


ELECTRICAL

New power being attached to the new mast we had installed on the back face of the house.



Fortis guys attaching the new power line to the existing lines in the alley (overhead)



Taking down the lines at the front of the house. The electrician then removed the old mast. Now we can have the stucco repaired.

Wednesday, April 15, 2009

WHAT A WEEKEND!!!

Obviously as it's Wednesday and I'm still talking about the weekend!!

The kitchen was installed on Monday. Myles and I missed out on visiting with everyone who was still around on Sunday so we could get a coat of paint on the wall before the kitchen went in and......it was the wrong color! It was the color I picked but definitely not what I was thinking it would look like. I wanted a very cool light grey/concrete color, it was more a light lilac color or purple as most people said when they walked in the kitchen. So the next morning after we had painted I decided that it had to be changed and rushed off to Benjamin Moore to pick a new color. Unfortunately while I was doing that the kitchen installer showed up and started installing the kitchen so I didn't have time to repaint. I did manage to get a couple of stripes done on Monday night as he wasn't quite finished.
So these pictures show the purple color, this is not the color! (Note on new color: when I was choosing the colors I had two grey colors and asked Mylo which one he liked, he picked one I picked the other. Mine was purple...we are now going with his choice and it's very nice. Damn it)

So the kitchen is partially in at this stage. We are very happy with the layout and the look of the cabinets. Installation, not so happy. But we have a deficiency walk through and everything will be dealt with then. One door was cracked and another warped so things like that. This is one of the main problems of dealing with a big box kitchen supplier, there are usually lots of deficiencies.

In the middle of the kitchen installation, the appliances arrived and it got very hectic, very quickly. I didn't notice the appliance guy start unwrapping the appliances in the truck before bringing them in. We still have tons of drywall dust everywhere (not good for appliances). So our contractor had to go by shrink wrap and bring it over to wrap the stove, managed to stop them from completely unwrapping the fridge.. Everything looks great. Our new washer and dryer set fit down the stairs with about 1/8" clearance on each side (they had to take these out of the boxes). The guys didn't think it was going to fit but I told them I had previously measured and they should just fit. And they did. Unfortunately I had to unplug the kitchen installer's extension cord each time they took something downstairs (the only plugs are downstairs right now)so he wasn't very happy. It was crazy for about an hour. But then everything was done.









Interesting story
We have met a few of our neighbors now and it seems that Gertrude Grybowski (the previous owner) was pretty famous around these parts. Gertie, as everyone referred to her as, grew up in the house with her parents, moved away to become a catholic nun, moved back to take care of her parents and ended up living in the family home for the rest of her life. She went to church everyday, was a hemophiliac and was well known and loved thoughout the neighborhood. One neighbor fondly recalled how Gerties neices and nephews (having no children of her own Gertie often took care of all her neices and nephews) would come knocking on their door stating that "Auntie Gertie is bleeding again".....and she would go over and help Gertie, call the ambulance etc. Everyone was very worried that when the house finally sold that it was going to be ripped down so they are all very happy that we renovated it. I told you it was an interesting story.....That's all we have found out so far. Oh and that she had a cherry tree taken down in the front yard (it was way over sixty years old). The area use to be an orchard so everyone had fruit trees. That's all we know so far but I think that's enough.
(Change: Ok we have finally figured it out, the home was built by the family (someone we don't know who) and when Gertie came to Kelowna to look after her parents she lived in the house and then stay there the rest of her life)

Wednesday, April 8, 2009

DRYWALL CONT....

The drywall has been put in upstairs. Drywall is very interesting; one day you can't really figure out what it's going to look like and then the next day you can see exactly what it's going to look like. So it's always a shock the first time you walk in after it's been installed. I've taken some pictures of the upstairs but the space is small therefore it's getting harder and harder to take pictures that make any sense. But thought I would upload them anyway.

This is the loft bedroom. Behind the red brick column there is a little walk in closet (it's very small, we had to shrink it so we could get what we wanted in the bathroom) but it's still a walk-in.....sort of!!
The door that is leaning on the wall was going to be reused (we're painting it white) but the painter seems to think that I won't be able to paint it, or it's not worth the effort of stripping it. He had me convinced but I've since changed my mind (sorry Mylo). I think that I can strip it down and paint it. As well as the jamb, it's going to be some work but they are lovely doors. The reason it is white is we don't have enough original baseboard to do the upstairs so it is getting new white baseboards (6" high) so the door needs to be white as well.



View of the bathroom looking towards where the vanity will be. The build out on the right is framing required for the stair headroom clearance, we just took it all the way up to the ceiling with shelving. The plywood table on the left is covering the clawfoot tub.



This view is looking at the shower (to the left) and the toilet (straight ahead. There is an attic hatch door in the corner (right side) that we could not remove but I think I'll put some sort of peice of furniture in front of it. We are keeping the doors (there is another one in the bedroom) just adding weatherstripping and new hardware.



This view looks directly into the shower. The shelving above the stairwell is on the left and the right is the toilet location. We added some niches into the wall and they have caused all sorts of problems. They still are not correctly drywalled at this point even though the drywallers have left and the house is being mudded and taped right now. But they will. Why they didn't just do it????? Alot of whining on site and excuses on site right now but it's just hurts them in the long run as they just have to come back on there own time. (Sub-contractors are a total pain in my ass, just quit your bitching and get it done!!- M.)



The deck is almost complete, still needs the stairs and a box around the gas meter.



Close up of the new deck...



The flooring patch work started today. It's going to take him awhile but he's doing a really nice job of fixing & patching (using some existing wood, some salvaged wood and some new wood). He's a little upset, but it doesn't have to do with our floor, I guess he's mad at the drywall taper who dropped mud on his tool belt or something. But at least he's not complaining about our floor! It will be really beautiful natural Douglas Fir when it's finished!! Pretty stoked on the floor.



I've never done alot of drywall work in a renovation before. Little bits here and there so this was a bit of a shock. The mud/tape is everywhere, mudderss have got to be the messiest trade I've ever seen. What's on the wall looks great just that there is mud everywhere!!!! Like, everywhere!!! Talking to our contractor tomorrow about it. (It's a renovation..........it's messy!! Don't worry about it!! Yeah, not so much -M)



Does anyone know what this is, I have quite abit of it coming up. I know it's probably impossible to tell but thought someone might know.



And spring has arrived, here's a pretty picture of flowers in the front garden.

Monday, April 6, 2009

PUPPIES!

Everyone this is Gibson...



Or....one of these is Gibson...........still hard to tell. There are four black males, one of them is Gibson!



This is the little girl S & P puppy that the owner is hoping Myles and I take as well. She really loves her and wants her to grow up in the area as well as with a brother. I think she likes us too!!! She is so cute and her name would be Stella. Shouldn't be naming dogs we don't own yet. Dana (the breeder) only has owners for five right now so four still need good homes.....hey Brad and Chris????



Dana has nicked named this one "Dr. Evil" already. Although he doesn't look it here he's already a mischevious little guy



So cute....seeing puppies sure helped calm my renovation stress!!

Sunday, April 5, 2009

DRYWALL, DECK & OTHER STUFF....

Things are moving along very quickly right now so having problems keeping up with pictures. The new stairs for the basement were installed on Thurs. Felt bad for all the trades having to go up and down the other stairs (with about 3'6" headroom clearance) and now we have new stairs (with about 6'-0" headroom) and they are done most of their work now! The are pretty steep but we are going to add a handrail so they should be fine, Myles doesn't even have to duck anymore.




The deck is almost complete in this picture. I can't keep up with the construction as the deck is now complete, I'm a couple of days behind. The cedar decking smells wonderful I wish the deck would smell like that forever but it won't. The deck is a great size, now that's it finish we can stand on it and figure out where to put things and figure out landscaping etc.





The main floor is almost completely drywalled now. We have had to add some drywall here and there (1/4") on existing walls as construction really did alot of damage. With all the drilling and hammering the house was shook up at bit which is not good for old plaster. So some walls were just too cracked. So they are just putting an sheet of 1/4" (usually they use 1/2") on top. Looks very different after drywall. You get so use to seeing it open and then suddenly it's closed off. They have started upstairs as well but haven't taken pictures yet.




One of the splurges for the house was a new tankless hot water heater, hot water on demand. Very excited to never run out of hot water. And will help out on our gas bills as we don't have to keep a tank full of water hot now. This installation cause a bit of a fiasco as I showed up one morning and there is a big vent on the front of the house. Again bascially an issue of trades not talking to each other and just installing stuff without any thought to asethetics or client opinion. So I freaked out...nicely. There is a basement slider window (openable) right by the location where the tankless hot water heater was going to be installed. The venting for the tank has to be a certain distance from an openable window. So when the installer was there he saw the basement window and went ahead and installed the vent out the front of the house. Unfortunately the builder and Myles and I had already discussed this window (as all four basement windows were ordered incorrectly) and that when they ordered new windows we were going to order than particular one as a fixed window (unopenable - is that a word?) We were prepared to pay for that window (would have been cheap) but since it was never communicated to the plumber we have told our builder to either move it (which I don't think will happen) and we will still cover the cost of the new window or he leaves, plants some landscaping around the vent outside and we don't cover the cost of that window. Confusing I know.



Other than that, drywall, taping and mudding happens all this week. Probably the new front porch as well. Next weekend we will be painting as much as we can before kitchen and plumbing fixtures are installed. Next Monday kitchen is installed and appliances arrive, next wednesday is granite templating and flooring begins. And Myles and I are in Vancouver for Tuesday/Wednesday, wow, that's bad timing. Oh well.