Thursday, March 26, 2009

WINDOWS & DOORS

Old windows & Doors....



Without windows, still with old doors......



With new windows and doors......finally!



So we basically replaced the windows with the exact same look as the old wood ones. I would have loved to have replaced them with wood windows but the cost of wood is about twice as expensive. We do have a funky new application on the windows that doesn't cost very much, it's call "Neat glass". Supposedly (at least it's what they say) we will never have to wash the exterior glass of the windows. I have absolutely no idea how it works, I will look into it and pass on the information. So anyone who is thinking of replacing windows can ask us in the next years to come is this was a good add on or not.



The new front door, the color is great, it took us a long time to pick that flesh tone color. Kidding. This is a masonite door, basically a plastic door with a wood grain finish that you can stain (gel stain) to look like wood. It is very nice when completed, although they look pretty horrible until stained. Again a wood door would have been perferrable but the house faces directly south and without any protection the wood have warped and faded eventually. And you can sort of notice but the electrician mounted the new exterior light junction boxes uneven. Guess our house isn't level from the inside to the outside.

And thanks for the all the responses but the general concensus is that it's rhubarb....was hoping for something alitte more exciting....

Wednesday, March 25, 2009

VERY BUSY WEDNESDAY

So today was a busy, busy, busy day at the house......
I (Cath) showed up about 10am and there was alot going on: the framer (putting in the sono tubes for the concrete for the deck), the plumbers, the insulation guys, the HVAC contractor and the window installers. That's alot in 1400 SF.
This is the upstairs, all insulated, with the exception of the sloped portion which is being spray foamed tomorrow. If you look to the background of the first photo, you can see the guys discussing some insulation issues regarding some niches that we had added to the wall beside the toilet. The insulaters just stuff some insulation in the niches not knowing what they were for. When told, they basically had the attitude, have the framers rip it out so we can correctly run the VB (vapour barrier) through and around the wall. The framers came up with another solution (more work for insulaters) but unfortunately they refused. Very interesting. So either the insulators are coming back or the framers are re-framing, who knows. They can work it out. Let's just say that Mylo was not very happy about that kind of attitude on site. It's the first time we've run into anyone being that way. It was bound to happen. Other than this, we have been completely happy with all our trades. Second plumbing inspection...passed. Some guys (in a smart car with "City of Kelowna" on the side) walks into the house, walks around then hands me a peice of paper with "proceed" on it and that's that, for now. Love inspectors....
The deck had some framing issues today (BC code) so the lower portion is alittle higher than we initially wanted it and there is only 1 step down from the high to the low part if that makes any sense. I guess the only thing I can say about this sort of stuff (changes due to construction constraints or code) is to make the decision on site right away, it's tough when things have to change, but unfortunately if you go away to think about it, it just delays the whole process. Just make a decision and live with it. That's what today was. Plumbing wanted to know what height to mount the spa jets in the shower? I have no idea, but it's up to us so....You would think they have standards for this sort of thing but not really.



The back yard after digging all the holes for the piles.








Windows being installed. It is very strange to look at a house with no windows in it. These photos were taken at 12:30pm and I was back there at 4pm and all the windows are in. Amazing.... (photos of new windows tomorrow)



Mom Thurlow do you have any idea was this is, it's coming up in the back garden. I'm trying to protect it but it's in a path of contractor travel. Very hard to do damage control.



Crocuses are up and blooming....

Tuesday, March 24, 2009

WHAT'S HAPPENING THIS WEEK....

Ongoing progress:

Our contractor is back (he had to attend his grandmother's funeral last week in Manitoba) so he has been very busy trying to get everything up and running again. Besides HVAC not alot happened last week.
Monday we had our framing inspection, we passed with some minor upgrades. Building inspectors can be really friendly and nice or they can be the other kind and unfortunately for Mylo and I we have the other kind. Mylo did all the talking, I stood outside (I don't deal well with this aspect of the process), he is much more diplomatic. So a few more posts in the basement and some extra framing in the attic for plumbing lines and ventilation and we are done with framing. We are going to be adding some spray foam insulation to the sloped portion of the upstairs (as per the inspectors request) which should be starting tomorrow. Mr. building inspector tried to have us furr out the sloped portion of the ceiling (add some more framing to increase the R value) but Myles said "forget it". So we are picking our battles now.

Note: Well, that's not quite how it happened, but close. I basically told the inspector that we were doing it solely at his request, more to appease him than anything. I also told him that we didn't have to do anything at all because according to the BC Building Code, as long as we don't "decrease the level of performance of the existing building..." we are fine. I think he forgot that Cath and I are in the industry. So that saved us a couple thousand bucks!! - M

- Pictures will come tomorrow...
- They have dug five big holes in our back yard for the footings & piles of the deck.
(No trees were harmed during this process!!)
- Concrete being poured tomorrow.
- Window installation has begun, presently 2 have been installed.
- Insulation begins tomorrow.
- The new furnace should arrive this week and all ducting to be completed.
- Our kitchen is ready but we aren't so.......

They are slowly putting our house back together.......and now......PUPPIES!!!!!


Right after a feeding....





Monday, March 16, 2009

COLORS & FINISHES....AND PUPPIES

Colors & Finishes

It's hard to capture the true colors but this is pretty close. Right side: Kitchen, Dining and Living Room. Left side: Bathrooms. The blue color at the top is the exterior color (although it looks dark it's a light grey blue).




Puppies.....


RESTORATION

Wall Mounted Sink




These are the original sink legs for the wall mounted sink in the main floor bathroom. I decided to re-use the existing sink as it was in good condition, I liked the retro look of the legs and towel bars and, most importantly, it fit well in such a small space. But, unfortunately one of the legs was bent so I did a bunch of searching on the internet and managed to find a site on restoring old retro style bathrooms, called "Save the pink bathroom" www.savethepinkbathrooms.com, which lead to www.retrorenovation.com, another cool blog. It has some information on where to purchase sink legs and they were only $25.00....wow hey! Not so..... I also needed to buy a corner shower curtain rod. A straight shower curtain would run straight into the window so it had to bend and return back to the wall. So I find this strange shower curtain at the same site that I found the legs, for only $90.00!! (kay, that's a bit expensive for a shower curtain rod but we had no choice). Anyways so I ordered it and wasn't really paying attention. What started as $135.00 worth of product eventually cost us $450.00 (shipping, duty, the dollar!!). Let's just say that I'm not allowed to order anymore strange products from the US anymore. But I have sink legs!!! But it's not over yet, I was simply going to use the existing side towel bars and had put them aside in one of the bedrooms and a grommet for one of the arms fell off and the guys (while cleaning) must have swept it up. And I can't find these towel arms anywhere. So I was alittle perturbed, my own fault for not getting them out of the house. But I have come up with a solution, I am going to use a portion of the old sink legs, which seems to work, not perfect but it will work. I hope.

Door Hardware



Here's my next issue. Replacing the door hardware or replacing the doors. The house has some beautiful wood doors, that match the fir floors that we would like to keep. The hardware is very old though. Two of them still have their keys as well. I have managed to find a site (in Canada this time, again, not allowed to order anything from the States!!) but it will still cost about $150.00/door.

But if we don't replace the hardware we have to replace the doors, which are all strange custom sizes. So, decisions, decisions. We will probably order the hardware, it would look really nice. I will order one first (shipping is very reasonable) and see if it works but from what dimensions we have it looks like they will fit.

IT'S OFFICIAL - WE'RE BEHIND SCHEDULE

So it finally happened we are officially behind schedule by at least 1 week, maybe closer to 2. A couple of things have happened that were beyond our control. First of all, HVAC....ahhhh, HVAC. Of all the things to be so complicated on a job. We took so long debating what to do about the heat pump vs. a high efficiency furnace that we sort of forgot about all the ductwork that is required to go along with that and of course they can't drywall until the ductwork is in. As well, the scope is much larger than we originally anticipated. Oops. We didn't realize that they need to change all our supply air ducts (on the main floor) to return air ducts and all the return air ducts to supply air ducts????? Silly, I know. In 1946 they put the heat registers on the inside of the house and the return air on the perimeters. Standard bldg. practice (by code) is the other way around. We should have looked at the HVAC system the same way we looked at the electrical and plumbing, replace the whole thing. So the mechanical contractor started Friday and will probably be a week. Secondly, and on a sadder note, our contractor's grandmother passed away so he is gone all this week in Manitoba. Impact (our builder) is a family run business by three brothers and one sister so the whole company is gone!!!!!
So no new pictures as HVAC is really not all that important....kay, I know it's important, all that heating & cooling, but it's just not interesting in pictures.
But on a good note, windows are suppose to be arriving anyday.....and they can probably start putting those in right away.

Wednesday, March 11, 2009

FRAMING COMPLETE!

This is the backyard right now.....what a mess!!! And we have a puppy coming in 7 weeks but we will be ready!! Hopefully!!


Living Room with framing complete. Plumbing inspection was Monday, we passed. Electrical & Framing inspecton are Friday, hopefully we'll pass but I'm sure we will. Windows are scheduled to arrive tomorrow and will probably start installation Friday. Drywall is scheduled to begin on Monday.


View from the dining room into kitchen. All framing is complete, the housing for the pot lights are in. Just waiting for HVAC, there is alittle bit of ducting to run upstairs.


Upstairs bedroom looking towards bathroom.


New clawfoot tub in upstairs bathroom. Had to be put in the bathroom right now as it wouldn't have fit through the existing door. Pain in the butt for the tile guy but unfortunately nothing we could do about it. Tub was installed incorrectly the first time but Mylo and I caught it and now it is in the correct position. We spent alot of time laying out the upstairs bathroom very carefully, as it is so small. But every single fixture had to move a couple of inches due to the location of the floor drains and the existing floor joist locations. But I think we worked it all out. One of those frustrating things you just can't control. Mylo and I also added in floor heating today to this bathroom. We were at a party on the weekend and someone had it installed in their kitchen and it was wonderful so we added it. Basically we are looking at our budget as what can wait can wait and what we won't be able to do afterwards we do now. We would never be able to add it later.



So cute!!!

Even cuter!!!